Engineering Geological & Geohazard Assessment Report/Geohazard Assessment Report
Standard Operating Procedure On The Conduct Of Geohazard Assessment
RAPID GEOHAZARD ASSESSMENT
- Scale of Output map: 1:100,00 to 1:50,000
- Information gathered during the field:
- Notations on possible causes or contributing parameters
- Impacts created such as:
- Number of affected households/properties
- Amount of damage (infrastructure, agriculture, etc)
- Field documentation (i.e. pictures and/or video footages)
- Depth and width of floodwaters
- Breadth of a slide
- Actions taken:
- Immediate information of the concerned local authorities or residents in the area about the possible risk involved
- Prepare technical report that would be immediately release to authorities (e.g. Secretary, Director, Regional Executive Director/Regional Director, NGA/LGU concerned) within appropriate time, and if necessary within 36 hours from the completion of work
RECONNAISSANCE GEOHAZARD ASSESSMENT
- Scale of Output map: 1:50,000
- Information gathered during the field:
- Historical accounts or records of incidence(s)
- Location(s) of previous or historical incidence(s) which is also plotted/pinpointed on the map
- Whenever necessary, sampling of rock /soil or any datable information is made for future analytical or laboratory works.
- All the communities or barangays within the project area are being covered for the purpose.
- Rate of completion depends on the area and number of concerns
- Team consists of:
- Four (4) geologist
- Two (2) geologic aides
- At least 80% of the total # of barangays in three (3) municipalities could be covered in two(2) weeks
(almost the same as rapid geohazard assessment but with some additional data such as)
Process Flow
To view please Click here